Skip to main content
Skip table of contents

20230816 - Unity Rollout Status Report

Current progress of Unity testing, development, and deployment.

RISKS

  1. Migration time

  2. Establish upgrade procedures and version controls for live clients on a single code version.

    1. Need agreement by all internal teams so that client communication is aligned.

    2. Needs to be clearly communicate to clients so they understand the future process.

    3. Need to confirm any risk associated with testing on one type of environment and going live on another.

    4. Need standard timeline of deploying latest branch, there is a calendar that a few have seen internally and gme/terra have seen

  3. For Unity-Upstream2

    1. We will need to have db loaded for each one to test regulatory in all the different states(8 total, possibly can exclude 2)

    2. Bank formats

    3. Land/Contract Management needs heavy regression (170/290 features were WPX)

  4. For Unity-Midstream1

    1. Bank formats

    2. Fixed assets

  5. Resource constraints internally

    1. Chris Peterson(M33) assisting in who and how to target on initial call. Continued discussion scheduled 7/10

    2. Services to begin assisting Midstream regression testing to meet Aug1 deadline

      1. Micah, Blake, Ryan putting together Midstream specific test cases

GAPS

  1. Release Notes (Jeff Gunter/Michael Ferrante actively working on)

    1. Need process put in place to combine deltas as new clients onboard to Unity

  2. Active projects versioning and communication

    1. action item: Sally to delegate communication out about releases and release notes coming

  3. Internal project box alignment

    1. Still need Raisa project and UAT setup for project team to start

      1. Raisa box created 8/23/23.

    2. schedule call with Vipul et al(frank, csms, sally) to discuss quick box break down to determine which can be shut down

  4. Rewrite SOC documentation for delivering patches, releases etc

    1. bring up to Erik Frazier, add to call

  5. Pre Unity to Unity db schema changes

    1. Clients with replica db’s need this level of detail for reporting/dashboards etc.

    2. This must be the source and destination for the respective client.

Internal Feedback/Questions

  1. Is there a way to create a dashboard in JIRA for clients on unity to know which code version is in their prod? who should own that creation? Vinay was supposed to create but hasn’t been shared. Vipul sent

  2. We are forming teams of 2-3 to reach out to next 20 clients.

  3. Timeline needed for midstream unity 2 merge.

    1. Mustang is a new client that will need Summit’s contract management code. No timeline is set still on mid1. can’t just do summit due to targa and some others lined up for future rollout

  4. There could be delay in rollout and unity items being worked while services burndown is happening

  5. Consistent OI issues

  6. WH Balancing documentation needed for Flywheel from 10.5.0

  7. How are we looking to resolve the space issue?

  8. What are we doing internally to resolve the issues we continue to experience on new roll outs?

    1. We have not had 1 clean Unity upgrade for any client.

Current Status

  1. LIVE CLIENTS

    1. TERRA (Live 5/22) Yellow

    2. GME (Live 5/22) Yellow

    3. IKAV (Live 6/12) Red

    4. Flywheel (Live 7/17) Green

    5. Highpeak (Live 7/31) Yellow

    6. King (8/1) Green

    7. Riverbend (8/7) Yellow

      1. Has OI issues currently.

  2. Vital (UAT-GO LIVE TARGET 8/18) Yellow

    1. 28 open tickets(12 code change, 13 support review, 3 awaiting feedback)

    2. client requested 6 old tickets be moved to Vital Unity organization that increased ticket count

    3. All critical for go-live tickets were completed and returned to Vital for testing

  3. Internal regression testing(QA)

    1. Upstream(Jaybee DB)

      1. Functional high risk: total = 133 (Untested - 127, Pass - 5, Fail-1)

    2. Midstream

      1. Eagleclaw (will not be our first midstream client on unity)

        1. total = 509(Untested - 60, Pass - 414, Fail-35)

    3. Transportation

      1. CHS

        1. 73 test cases Untested.

  4. Live clients' logged ticket count in backlog: 76

    1. Dev queue: 18

    2. Support queue: 44

    3. Waiting on DevOps: 2

    4. Waiting for Feedback (from client):11

    5. Assigned to reporting team: 1

Focus for Next Week

  1. Mid/Trans Unity1 regression testing - @a user coordinating additional resources from Services

  2. Determine how many clients we can take on internally for continuous and successful roll out of Unity

    1. Need follow up meetings surrounding FR2.0 and land

  3. Examine root cause for open tickets @a user and team

Future Process Improvements

  1. Build RACI matrix for future efforts for transparency of responsibilities across teams.

  2. Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.

  3. Continue to build out test cases for regression testing across the application.

    1. Add expected results to compare against for testers with limited functional knowledge.

  4. Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.

  5. Add code test coverage to eliminate lost functionality with future merges or code changes.

    1. During current round of testing multiple issues have re-emerged after originally fixed.

  6. Comprehensive and up-to-date check list of all tasks related to upgrades.

Important Links

Regression testing dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10080

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077

Clients in upgrade pipeline

Jaybee, TRG, Dugan

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.