RISKS
Migration time
Establish upgrade procedures and version controls for live clients on a single code version.
Need agreement by all internal teams so that client communication is aligned.
Needs to be clearly communicate to clients so they understand the future process.
Need to confirm any risk associated with testing on one type of environment and going live on another.
Need standard timeline of deploying latest branch, there is a calendar that a few have seen internally and gme/terra have seen
For Unity-Upstream2
We will need to have db loaded for each one to test regulatory in all the different states(8 total, possibly can exclude 2)
Bank formats
Land/Contract Management needs heavy regression (170/290 features were WPX)
For Unity-Midstream1
Bank formats
Fixed assets
Resource constraints internally
Chris Peterson(M33) assisting in who and how to target on initial call. Continued discussion scheduled 7/10
GAPS
Release Notes (Jeff Gunter actively working on)
Active projects versioning and communication
Internal project box alignment
Rewrite SOC documentation for delivering patches, releases etc
Internal Feedback/Questions
JIB close monitored closely by SME(Donnita) and time improvements were monumental(4+hours down to 48 minutes with more entries added that prior run).
“I want to let you and W support team know that JIB close went a lot smoother and faster this month compared to the last three previous months. I sure appreciate not having to stay up late trying to close JIB this month. Thank you again for your support.” -GME user
Division Order module had many challenges this week
Duplicates
Missing DOs in approval workflow
TIK
historical data cleanup needed
Consistent Open Invoice issues
WEDEVOPS-14017 (Vital UAT sync fatal)
WEDEVOPS-14580 (Terra Prod missing invoices after code deploys)
WEDEVOPS-146613 (IKAV prod sync fatal)
WEDEVOPS-14484 (GME acquistion environment sync fatal)- RESOLVED 7/7
Current Status
TERRA (Live 5/22) Yellow
Issues since go-live (48)
Closed-29, Code Change in progress-2, Support Review-10, Waiting for feedback-1, Waiting on CloudOps-3
GME (Live 5/22) Red
Issues since go-live (44)
Closed-22, Code Change in progress-4, Support Review-14, Waiting for feedback-2, Waiting on CloudOps-2
IKAV (Live 6/12) Green
Issues since go-live (49)
Closed-23, Code Change in progress-4, Support Review-16, Waiting for feedback-5, Waiting on CloudOps-1
Flywheel (UAT) Green
4 open tickets(3 support review, 1 waiting on cloudops)
Rev and JIB testing at 70% complete
Vital (UAT) Yellow
7 open tickets(4 code change, 2 support review, 1 waiting on DevOps)
potentially move to upstream phase 2, discussing go-live timeline next week
Riverbend (UAT) Green
2 open tickets (both in support review)
Highpeak (UAT) Yellow
8 open tickets (all in support review)
Internal regression testing(QA)
Upstream
Phase 2 has not started. Jaybee will likely be test database
Midstream
Eagleclaw
96% complete (High risk)
15% complete remaining test cases(492 untested)
Transportation
N/A
Live clients' logged ticket count in backlog: 75
Dev queue: 15
Support queue: 44
Waiting on DevOps: 6
Waiting for Feedback (from client):10
Future Process Improvements
Build RACI matrix for future efforts for transparency of responsibilities across teams.
Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.
Continue to build out test cases for regression testing across the application.
Add expected results to compare against for testers with limited functional knowledge.
Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.
Add code test coverage to eliminate lost functionality with future merges or code changes.
During current round of testing multiple issues have re-emerged after originally fixed.
Important Links | Regression testing dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10080 Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077 |
Clients in upgrade pipeline | Jaybee, AEC |