RISKS
Migration time
Establish upgrade procedures and version controls for live clients on a single code version.
Need agreement by all internal teams so that client communication is aligned.
Needs to be clearly communicate to clients so they understand the future process.
Need to confirm any risk associated with testing on one type of environment and going live on another.
Need standard timeline of deploying latest branch, there is a calendar that a few have seen internally and gme/terra have seen
For Unity-Upstream2
We will need to have db loaded for each one to test regulatory in all the different states(8 total, possibly can exclude 2)
Bank formats
Land/Contract Management needs heavy regression (170/290 features were WPX)
GAPS
Release Notes (Jeff Gunter actively working on)
Active projects versioning and communication
Internal project box alignment
Rewrite SOC documentation for delivering patches, releases etc
Internal Feedback/Questions
WEMAIN-11141 and WEMAIN-11144
Not an issue pre-v10
Current Status
TERRA (Live 5/22) Yellow
Issues since go-live
Closed-15, Code Change in progress-4, Support Review-6, Waiting for feedback-1, Waiting on CloudOps-1
GME (Live 5/22) Yellow
Issues since go-live
Closed-13, Code Change in progress-2, Support Review-12, Waiting for feedback-1, Waiting on CloudOps-2
IKAV (Live 6/12) Green
Issues since go-live
Closed-3, Code Change in progress-3, Support Review-11, Waiting for feedback-0, Waiting on CloudOps-2
Flywheel (UAT) Green
6 open tickets(3 code change, 3 support review), 7 Closed
Rev and JIB testing at 70% complete
Vital (UAT) Yellow
4 open tickets(3 supprt review, 1 waiting on DevOps)
potentially move to upstream phase 2
Riverbend (UAT) Green
1 reported issue
Highpeak (UAT) Yellow
One critical issue reported
Internal regression testing(QA)
Flywheel (High Risk)
no change from last week
Untested - 76, Pass - 69, Blocked - 1, N/A - 10, Unable to test - 3
Vital (Full Test Suite)
Only one new test case tested since last week
Untested - 501, Pass - 361, Fail - 18, Blocked -8 , N/A- 42, In-Progress- 2
Live clients' logged ticket count in backlog: 36
Dev queue: 13
Support queue: 24
Focus for Next Week
Continue Vital & Flywheel regression testing - QA
Mid/Trans Unity1 to begin regression testing - QA
Examine root cause for open tickets @a user and team
Future Process Improvements
Build RACI matrix for future efforts for transparency of responsibilities across teams.
Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.
Continue to build out test cases for regression testing across the application.
Add expected results to compare against for testers with limited functional knowledge.
Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.
Add code test coverage to eliminate lost functionality with future merges or code changes.
During current round of testing multiple issues have re-emerged after originally fixed.
Notes |
|
|---|---|
Important Links | Regression testing dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10080 Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077 |