20230524 - Unity Rollout Status Report

Current progress of Unity testing, development, and deployment. Current clients targeted are Terra, GME, IKAV, Vital, Flywheel.

RISKS

  1. Need continuous performance optimization plan for GME and Terra after go-live

    1. Outstanding critical items getting addressed on latest version(IKAV)

  2. Migrations

    1. IKAV Prod-if similar to Terra, could run into downtime during business hours

    2. IKAV UAT-needs latest GME migration

    3. Terra-needs latest GME migration

  3. Establish upgrade procedures and version controls for live clients on a single code version.

    1. Need agreement by all internal teams so that client communication is aligned.

    2. Needs to be clearly communicate to clients so they understand the future process.

    3. Need to confirm any risk associated with testing on one type of environment and going live on another.

GAPS

  1. Release Notes

  2. Active projects versioning and communication

Current Status

  1. TERRA IS LIVE

    1. Bumpy start. Need to address why migration took 72 hours vs 36.

    2. Wins: no critical issues and increased performance noticed by users

  2. GME IS LIVE

    1. Migration was very quick(completed 11pm Friday night)

    2. EAG began testing Sunday. Critical items showed up in Prod causing resource constraints around the clock for 3 days specific to GME

    3. Prod down 5/24 @ 1:05pm

  3. Internal regression testing(QA)

    1. Flywheel - Untested - 77, Pass - 69, Blocked - 1, N/A - 10, Unable to test - 3 (High Risk) -no change from last week

    2. Vital - Untested - 577, Pass - 305, Fail - 15, Blocked - 7, N/A- 39, In-Progress- 3(Full Test Suite)

  4. IKAV UAT

    1. 83% complete testing - 319 Pass, 10 Fails, 68 To Do

    2. 13 complete, 4 in code change

  5. Live clients' logged ticket count in backlog: 19

    1. Dev queue: 8

    2. Support queue: 11

  6. Flywheel UAT

    1. Only 2 tickets reported and already closed. One due to user error, the other DevOps procedure for SSO

    2. 17 - Pass, 55 - Untested (currently on JIB and Rev)

Focus for Next Week

  1. Continue Vital & Flywheel regression testing - TBD QA resource & @a user coordinating

  2. Riverbend UAT setups - waiting for Adnan to return

  3. Highpeak UAT discussions

  4. Focus on dev completion of issues across Scrum Teams - @a user coordinating

Future Process Improvements

  1. Build RACI matrix for future efforts for transparency of responsibilities across teams.

  2. Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.

  3. Continue to build out test cases for regression testing across the application.

    1. Add expected results to compare against for testers with limited functional knowledge.

  4. Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.

  5. Add code test coverage to eliminate lost functionality with future merges or code changes.

    1. During current round of testing multiple issues have re-emerged after originally fixed.

Notes

  1. Terra and GME UAT is ongoing

  2. IKAV UAT kicked off 4/24

  3. We have a dedicated v10 team with 3 engineers.

  4. Additional resources are available from other sprint teams as needed.

    1. Upstream, DO/Land, and Regulatory team are taking stories as capacity allows.

Important Links

Regression testing dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10080

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077