Current progress of 10.2.0 testing, development, and deployment. Current clients targeted are Terra, GME, IKAV, Vital, Flywheel.

RISKS

  1. Code freeze has not happened due to slow turnaround of oustanding tickets needed for GME go-live

  2. Terra reporting no noticeable improvement across DO functionality.

    1. Met to review performance and monitor. Plan to optimize has not been defined yet.

  3. IKAV testing on Azure has experienced multiple issues that cannot be reproduced internally on functionality already passed internally and at other client UAT.

    1. We are not able to identify the cause of issues yet whether environmental or data set driven.

  4. Code freeze is currently planned for EOW or 5/8 but have 25 that are currently In Progress or In Review that will need to be fully completed before then.

    1. 4 critical for GME go-live

    2. 2 critical for Terra go-live

  5. Clients using EAG to test cause additional WES resource burden to validate issues.

  6. Initial regression testing on Flywheel and Laredo have found multiple JIB issues that were previously thought resolved (could be dataset related but unknown at this time).

  7. Establish upgrade procedures and version controls for live clients on a single code version.

    1. Need agreement by all internal teams so that client communication is aligned.

    2. Needs to be clearly communicate to clients so they understand the future process.

    3. Need to confirm any risk associated with testing on one type of environment and going live on another.

Current Status

  1. Significant backlog of items to test for code freeze.

  2. IKAV Tie-out testing

    1. Revenue company processes delayed due to environmental constraints. Will be done in parallel with IKAV UAT testing.

  3. Functional regression

    1. IKAV - 50 Untested, 2 Failed

    2. Flywheel - 69 Pass, 0 Failed, 77 Untested (High Risk Test Suite)

    3. Vital - 165 Pass, 5 Failed, 755 Untested (Full Test Suite)

  4. IKAV UAT

    1. 67% complete testing - 262 Pass, 13 Fails, 127 To Do

  5. Client logged ticket count - total

    1. GME - 4 code change, 4 complete, 3 awaiting feedback, 4 in review, 23 closed no action (38)

    2. Terra - 4 code change, 10 complete, 4 support review, 11 close no action (29)

  6. Flywheel UAT

    1. Environment setup complete 5/10/23

Focus for Next Week

  1. Continue Vital & Flywheel regression testing - TBD QA resource & @a user coordinating

  2. Riverbend UAT setups

  3. Highpeak UAT discussions

  4. IKAV OpenInvoice invoice sync testing with fake server - @a user coordinating

  5. Focus on dev completion of issues across Scrum Teams - @a user coordinating

  6. Monitor client UAT testing - @a user and CSMs coordinating

  7. Finalize dates for Pilot Clients for future Unity Releases - @a user and @a user coordinating

Future Process Improvements

  1. Build RACI matrix for future efforts for transparency of responsibilities across teams.

  2. Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.

  3. Continue to build out test cases for regression testing across the application.

    1. Add expected results to compare against for testers with limited functional knowledge.

  4. Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.

  5. Add code test coverage to eliminate lost functionality with future merges or code changes.

    1. During current round of testing multiple issues have re-emerged after originally fixed.

Notes

  1. Terra and GME UAT is ongoing

  2. IKAV UAT kicked off 4/24

  3. We have a dedicated v10 team with 3 engineers.

  4. Additional resources are available from other sprint teams as needed.

    1. Upstream, DO/Land, and Regulatory team are taking stories as capacity allows.

Important Links

Regression testing dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10080

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.