20230414 - 10.2 Rollout Status Report
Current progress of 10.2.0 testing, development, and deployment. Current clients targeted are Terra, GME, and IKAV.
RISKS
Terra reporting no noticeable improvement across DO functionality.
Coordinating meeting to monitor environment for further investigation.
Production Accounting tie-out still in progress for both Terra and IKAV waiting on a config change for Terra and analysis for IKAV.
Client reported issues that are data dependent require db refreshes to internal environments.
Currently this can take a full day or more for Terra and GME.
Resources on COLO are strained and cannot support additional instances of large clients.
Establish upgrade procedures for live clients on a single code version.
Need agreement by all internal teams so that client communication is aligned.
Needs to be clearly communicate to clients so they understand the future process.
Current Status
IKAV regression testing proceeding well for 4/24 deadline.
Tie-out testing
JIB tie outs complete
Revenue asset tie outs complete
Production asset tie out in progress with Nathan investigating issues
Revenue company processes to begin next week
Functional regression
144 Pass, 1 Fail on High Risk
64 Pass, 2 Remaining tests on Low Risk
178 pass, 129 Remaining tests on Regular functional cases
246 pass, 3 Fails, 171 Remaining UI test
Terra and GME both successfully synced to Enverus for OpenInvoice.
Client logged ticket count - 32 total
GME - 3 code change, 1 complete, 3 awaiting feedback, 7 in review, 7 closed no action
Terra - 4 code change, 1 support review, 6 close no action
Performance fixes still in progress.
Release Revenue Payments
Posting Engine performance
Aligned UAT environments with PROD specs (verified with DevOps)
Using COLO box for GME caused outage when our VPN went down.
IKAV testing environment is not available yet.
Focus for Next Week
Finalizing IKAV regression testing - @a user & @a user coordinating
Complete IKAV tie-out - @a user coordinating
IKAV OpenInvoice invoice sync testing with fake server - @a user coordinating
Focus on dev completion of issues across Scrum Teams - @a user coordinating
Monitor client UAT testing - @a user and CSMs coordinating
Ensure IKAV environment is setup and available for testing prior to 4/24- @a user coordinating
Future Process Improvements
Build RACI matrix for future efforts for transparency of responsibilities across teams.
Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.
Continue to build out test cases for regression testing across the application.
Add expected results to compare against for testers with limited functional knowledge.
Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.
Add code test coverage to eliminate lost functionality with future merges or code changes.
During current round of testing multiple issues have re-emerged after originally fixed.