20230414 - 10.2 Rollout Status Report

Current progress of 10.2.0 testing, development, and deployment. Current clients targeted are Terra, GME, and IKAV.

RISKS

  1. Terra reporting no noticeable improvement across DO functionality.

    1. Coordinating meeting to monitor environment for further investigation.

  2. Production Accounting tie-out still in progress for both Terra and IKAV waiting on a config change for Terra and analysis for IKAV.

  3. Client reported issues that are data dependent require db refreshes to internal environments.

    1. Currently this can take a full day or more for Terra and GME.

    2. Resources on COLO are strained and cannot support additional instances of large clients.

  4. Establish upgrade procedures for live clients on a single code version.

    1. Need agreement by all internal teams so that client communication is aligned.

    2. Needs to be clearly communicate to clients so they understand the future process.

Current Status

  1. IKAV regression testing proceeding well for 4/24 deadline.

    1. Tie-out testing

      1. JIB tie outs complete

      2. Revenue asset tie outs complete

      3. Production asset tie out in progress with Nathan investigating issues

      4. Revenue company processes to begin next week

    2. Functional regression

      1. 144 Pass, 1 Fail on High Risk

      2. 64 Pass, 2 Remaining tests on Low Risk

      3. 178 pass, 129 Remaining tests on Regular functional cases

      4. 246 pass, 3 Fails, 171 Remaining UI test

  2. Terra and GME both successfully synced to Enverus for OpenInvoice.

  3. Client logged ticket count - 32 total

    1. GME - 3 code change, 1 complete, 3 awaiting feedback, 7 in review, 7 closed no action

    2. Terra - 4 code change, 1 support review, 6 close no action

  4. Performance fixes still in progress.

    1. Release Revenue Payments

    2. Posting Engine performance

  5. Aligned UAT environments with PROD specs (verified with DevOps)

    1. Using COLO box for GME caused outage when our VPN went down.

    2. IKAV testing environment is not available yet.

Focus for Next Week

  1. Finalizing IKAV regression testing - @a user & @a user coordinating

  2. Complete IKAV tie-out - @a user coordinating

  3. IKAV OpenInvoice invoice sync testing with fake server - @a user coordinating

  4. Focus on dev completion of issues across Scrum Teams - @a user coordinating

  5. Monitor client UAT testing - @a user and CSMs coordinating

  6. Ensure IKAV environment is setup and available for testing prior to 4/24- @a user coordinating

Future Process Improvements

  1. Build RACI matrix for future efforts for transparency of responsibilities across teams.

  2. Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.

  3. Continue to build out test cases for regression testing across the application.

    1. Add expected results to compare against for testers with limited functional knowledge.

  4. Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.

  5. Add code test coverage to eliminate lost functionality with future merges or code changes.

    1. During current round of testing multiple issues have re-emerged after originally fixed.

Notes

  1. Terra and GME UAT have begun testing this week

  2. We have a dedicated v10 team with 3 engineers.

  3. Additional resources are available from other sprint teams as needed.

    1. Upstream, DO/Land, and Regulatory team are taking stories as capacity allows.

Important Links

IKAV regression testing dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10080

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077