20230331 - 10.2 Rollout Status Report

Current progress of 10.2.0 testing, development, and deployment. Current clients targeted are Terra, GME, and IKAV.

RISKS

  1. Environmental self-inflicted wounds continue to occur.

    1. Fatals due to memory and disk space.

    2. UAT sizing is not equivalent to PROD environments or internal testing environments.

  2. Establish upgrade procedures for live clients on a single code version.

    1. Need agreement by all internal teams so that client communication is aligned.

    2. Needs to be clearly communicate to clients so they understand the future process.

  3. IKAV regression just started 3/29 was due to start 3/1 per plan.

    1. Delay of over 3 weeks means teams will potentially have to work outside business hours to achieve target of 4/17 completion date.

    2. IKAV is slated for UAT in 1 week total. We will need to turn around any issues ASAP to achieve this kind of timeline.

  4. Production Accounting tie-out still unresolved but identified the two issues that will resolve all remaining tie-out differences.

  5. OpenInvoice issues on client environments are notoriously hard to determine source.

  6. Client reported issues that are data dependent require db refreshes to internal environments.

    1. Currently this can take a full day or more for Terra and GME.

    2. Resources on COLO are strained and cannot support additional instances of large clients.

Current Status

  1. Internal IKAV environment is up and running as of 3/29.

  2. Tie-out progress

    1. Terra Production have differences and still in work per note in RISKS.

    2. JIB testing is complete and passed.

    3. No IKAV tie-outs have started. Environments are being setup now.

  3. Migration issue is being resolved by Nathan and is testing.

    1. Temporary solution for GME without re-migration was tested internally and is ready for client.

  4. Client logged ticket count - 15 total

    1. GME - 2 confirmed bugs, 4 closed no action, 2 under investigation, 1 future resolution

    2. Terra - 2 environmental, 2 closed no action, 2 performance enhancement

  5. Performance fixes still in progress:

    1. Deleting records from GLD in JEs

    2. Release Revenue Payments

    3. Posting Engine performance

Focus for Next Week

  1. Heavy IKAV regression testing - @a user & @a user coordinating

  2. Begin IKAV tie-out - @a user coordinating

  3. Focus on dev completion of issues across Scrum Teams - @a user coordinating

  4. Monitor client UAT testing - @a user and CSMs coordinating

Future Process Improvements

  1. Build RACI matrix for future efforts for transparency of responsibilities across teams.

  2. Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.

  3. Continue to build out test cases for regression testing across the application.

    1. Add expected results to compare against for testers with limited functional knowledge.

  4. Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.

  5. Add code test coverage to eliminate lost functionality with future merges or code changes.

    1. During current round of testing multiple issues have re-emerged after originally fixed.

Notes

  1. Terra and GME UAT have begun testing this week

  2. We have a dedicated v10 team with 3 engineers.

  3. Additional resources are available from other sprint teams as needed.

    1. Upstream, DO/Land, and Regulatory team are taking stories as capacity allows.

Important Links

IKAV regression testing dashboard - TBD

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.