20230324 - 10.2 Rollout Status Report

Current progress of 10.2.0 testing, development, and deployment. Clients targeted are Terra, GME, and IKAV.

RISKS

  1. Issue found with migration that could invalidate the GME and Terra testing databases.

    1. Proposed solution that should allow us to keep existing databases and resolve issue.

  2. Production Accounting tie-out still unresolved with effort going on almost 1 month.

  3. JIB tie-out being held up by a posting issue. Based on data review JIB appears clean on GME and Terra.

  4. IKAV regression has not started.

    1. IKAV is slated for UAT in 1 week total. We will need to turn around any issues ASAP to achieve this kind of timeline.

  5. Environmental issues delayed both GME and Terra UAT start dates.

  6. Client reported issues that are data dependent require db refreshes to internal environments.

    1. Currently this can take a full day or more for Terra and GME.

    2. Resources on COLO are strained and cannot support additional instances of large clients.

  7. OpenInvoice testing was done with Fake Server internally. API testing will only be done in UAT.

  8. No GIS testing capabilities at this time.

Current Status

  1. Internal IKAV environment is being migrated and expected to be available by Monday

  2. Tie-out progress

    1. Terra Production have differences and still in work per note in RISKS.

    2. JIB is clean on GME and Terra appears to be as well. Last validation is waiting on a fix to the posting engine for the JIB JE.

    3. Created 4 tie-out scripts (posted on Confluence) that can be used by our teams in services or QA to do future JIB validations for testing or implementation.

  3. Revenue check file issue is now resolved. GME issue that was noted is related to migration issue listed in RISKS.

  4. Migration issue is being resolved by Nathan with a temp solution that allows us to maintain existing migrated database to not interrupt Client testing.

  5. Tickets completed - 9 stories for 18 points

  6. Open tickets - 21 tickets (3 - “To Do”, 10 - “In Progress”, 4 - “In Review”)

    1. To Do - 2 are performance/stability related, 1 is a cleanup task

Focus for Next Week

  1. Begin IKAV regression testing - @a user coordinating

  2. Finalize JIB Tie-Outs for Terra - @a user coordinating

  3. Focus on dev completion of issues across Scrum Teams - @a user coordinating

  4. Monitor client UAT testing - @a user and CSMs coordinating

Future Process Improvements

  1. Build RACI matrix for future efforts for transparency of responsibilities across teams.

  2. Add automation for the “easy” wins like UI testing to eliminate almost 30% of the testing effort.

  3. Continue to build out test cases for regression testing across the application.

    1. Add expected results to compare against for testers with limited functional knowledge.

  4. Have defined performance testing with PROD comparable environments to provide better expectations to clients when taking code.

  5. Add code test coverage to eliminate lost functionality with future merges or code changes.

    1. During current round of testing multiple issues have re-emerged after originally fixed.

Notes

  1. Terra and GME UAT have begun testing this week

  2. We have a dedicated v10 team with 3 engineers.

  3. Additional resources are available from other sprint teams as needed.

    1. Upstream, DO/Land, and Regulatory team are taking stories as capacity allows.

Important Links

Full details around testing provided here - Testing Tracker - v10.2 Test Metrics

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.