20230203 - 10.2 Rollout Status Report

Current progress of 10.2.0 testing and development with target of 2/28 completion. Clients being tested against are VEF, Terra, and GME.

Current Status

  1. All COLO boxes are now created for UI and tie-out testing (Terra just completed yesterday)

  2. Added additional UI test cases for all screens

  3. Tickets completed - 14 stories for 31 points

  4. Open tickets - 34 tickets

Focus for Next Week

  1. UI Testing on VEF project box - @a user coordinating

  2. Functional regression testing against GME & Terra project boxes - @a user coordinating

  3. Tie-Outs for GME, Terra, and GME - @a user coordinating

RISKS

  1. Bug resolution is significantly outpaced by ticket creation.

  2. OpenInvoice testing will have to be done with Fake Server internally.

  3. No GIS testing capabilities at this time.

Notes

  1. @a user is going to clean up UI tracker to prioritize screens and remove those not relevant for 10.2.0 testing.

  2. SMEs from the CX team are assisting in functional testing with @a user updating the tracker based on their testing.

  3. We have a dedicated v10 team with 3 engineers.

  4. Additional resources are coming from other sprint teams who lack priority stories.

    1. Currently, the Upstream team has queued up v10 tickets.

Important Links

Full details around testing provided here - Testing Tracker - v10.2 Test Metrics

Release 10.2.0 Dashboard - https://wenergysoftware.atlassian.net/jira/dashboards/10077

Total Test Cases

** High Risk Functional Tests are being done for each client uniquely. This count represents triplicate of the number of tests. One set per client.