20230127 - 10.2 Rollout Status Report

Current progress of 10.2.0 testing and development with target of 2/28 completion. Clients being tested against are VEF, Terra, and GME.

Completed

  1. COLO boxes created and verified for GME

  2. COLO tie-out boxes for VEF verified

  3. Consolidated tracker created in Confluence

  4. Tickets completed - 9 stories for 23 points

Past Due

  1. COLO boxes for Terra - delay due to DB migrations

Focus for Next Week

  1. Complete Terra migrations on COLO boxes - @a user coordinating

  2. Complete BigInt Conversion migration for all v10.2 DBs - @a user coordinating

  3. Regression testing across all clients - @a user coordinating

  4. Tie-Outs for VEF and GME @a user coordinating

Notes

  1. The Regression tracker is a consolidation of existing trackers and UAT cases from Implementation Projects.

  2. We have a dedicated v10 team with 3 engineers.

  3. Additional resources are coming from other sprint teams who lack priority stories.

    1. Currently, the Upstream team has queued up v10 tickets

Important Links

Testing tracker - https://wenergysoftware.atlassian.net/l/cp/46fA4vHk

JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.